Traffic congestion relief and ice removal coming to Alex Fraser Bridge, says Province

Alex Fraser Bridge as viewed from the SkyTrain bridge.
Photo by Rattan Mall

MOTORISTS who rely on the Alex Fraser Bridge will benefit from two projects going to tender on Wednesday.

The first is a new project to install a cable collar system for ice removal this winter.

The second is for elements of the $70-million Alex Fraser Bridge capacity improvement project.

“Last winter, snow and ice on the Alex Fraser Bridge’s cables forced several closures, which inconvenienced thousands of commuters. Adding a cable collar system to clear snow will improve the reliability of the bridge,” said Transportation and Infrastructure Minister Claire Trevena. “As well, adding an additional lane with a moveable barrier to the bridge will reduce rush-hour queues and save commuters valuable time each day.”

“Many Delta residents rely heavily on the Alex Fraser Bridge,” said Delta North MLA Ravi Kahlon. “The extra lane, with its counter-flow barrier system, will save commuters valuable time each day, and the cable collar system is an important safety addition that will help keep the bridge open during the worst winter weather.”

The tender for the cable collar system closes in mid-September 2017, with the new system expected to be in place on the Alex Fraser Bridge by the end of December. The system will be similar to the one used successfully to remove snow and ice from the Port Mann Bridge’s cables, but will be operated manually from the bridge to ensure its effectiveness. This project is valued at approximately $5 million.

The same contract will include initial work on the Alex Fraser Bridge capacity-improvement project. This includes replacing the existing fixed median barrier with a temporary concrete median barrier in support of expanding the number of travel lanes on the bridge to seven.

As part of that project, the ministry is also in the process of procuring a moveable barrier system, including barrier transfer machines. Additional work to complete the project will be tendered this fall, with the new lane and moveable barrier expected to be operational in fall 2018.

“Traffic congestion infringes on the quality of life in our residential communities and restricts the lives of the thousands of workers in the Annacis Island and Tilbury business areas,” said Delta Mayor Lois E. Jackson. “These improvements are positive steps and demonstrate leadership towards finding a solution. We must continue to work together to promote dialogue about future transportation planning, leading to action on infrastructure improvements that benefit the entire region.”

The Government of Canada is contributing up to $33,965,000 through the Provincial-Territorial Infrastructure Component of the New Building Canada Fund toward the $70-million capacity-improvement project. The cable collar system is a separate project and is funded entirely by the Province.